Mortenson was selected by San Diego-based developer, EDF Renewable Energy to build the Spinning Spur II Wind Project located in Oldham County, Texas. Spinning Spur II marks the 21st project that REG has built in the Lone Star state to date and the 25th project for long-time customer, EDF.

Situated on 27 square miles of farmland, the 160.95-megawatt (MW) project was comprised of 87, 1.85 MW, 80-meter GE turbines. Mortenson’s overall scope of work included procurement, engineering and construction of all access roads, foundations, erection, collection system, O & M building, MET towers and wind tower generators. Mortenson’s Civil Group performed all earthwork activities.

GET IN TOUCH

Jeff Jackson Jeff Jackson Business Development Executive Email | 763.287.3524